Case Studies
Proven Solutions, Real Results
Shafdan Water Treatment Facility, Rishon Le’Zion, Israel
Breakthrough Technology for Water Treatment Facilities
CQM Water has successfully developed and deployed an innovative electrolytic chlorine production system that generates disinfectant directly from secondary effluents. This groundbreaking approach eliminates the need for hazardous chemical transportation, storage, and handling while providing on-demand chlorine production for water treatment applications.
Key Achievements
Pilot Phase Success: Initial testing of the SRDWB-1200 system at Shafdan facility demonstrated reliable production of 0.3% hypochlorite solution (3,000 PPM) with minimal power consumption (0.50kW/h) and consistent operational parameters.
Commercial Implementation: Following pilot success, a full-scale system featuring dual SRDWB14000 reactors now produces 3 kg chlorine/hour directly from secondary effluents, successfully replacing traditional hypochlorite systems with their associated regulatory and logistical challenges.
Remote Application Deployment: The technology has proven particularly valuable for remote irrigation reservoir applications, with the first installation at Gal-on reservoir (500,000 m³ capacity) producing 1.5 kg chlorine/hour and effectively maintaining adequate disinfection levels throughout 1,000 m³/h irrigation networks.
Ein Kerem, Jerusalem – Israel
Mekorot (Israel’s national water company) Jerusalem groundwater facility
CQM WATER on-site, brine-free electro-chlorination replaces liquid hypochlorite facility.
Ein Kerem 16 Pumping Station supplies approx. 150 cubic meters/hour of groundwater chlorides level – 45 ppm. The station is situated in close proximity to the national zoo parking lot. Following a successful pilot study conducted during 2015, Mekorot upgraded its gas chlorine facility to CQM WATER’s on-site sodium hypochlorite generation equipment.
By shifting to CQM WATER on-site hypochlorite generation technology, Mekorot benefits from several advantages, including:
Complete elimination of the risks associated with transporting & storing gaseous chlorine
Elimination of chemicals from the process (salt, soft water & cleaning acids)
60% reduction of operational costs
Reduction of DBPs.
retrofitting liquid hypochlorite with CQM WATER on-site, brine-free hypochlorite generation
Migdal 4 Pumping Station supplies 150-200 cubic meters/hour of ground water.
Due to its proximity to residential neighborhoods, Mekorot engineers decided to eliminate the transportation and storage of liquid hypochlorite by upgrading to on-site chlorine generation. This station is essential for the local water supply system and operates continuously.
Following the upgrade, Mekorot southern water supply unit reported a 60% reduction in maintenance costs compared to previous liquid chlorine systems at sites with similar characteristics.
Due to the successful upgrade to CQM WATER’s electro chlorination devices in Midgal 4, additional devices were ordered for several more groundwater facilities in the Southern Unit.
Mekorot groundwater facility retrofitting liquid hypochlorite with CQM WATER on-site brine add hypochlorite generation
Blum Pumping station supplies approx. 450 cubic meters/hour of ground water. Due to its proximity to the regional school, Mekorot engineers decided to eliminate the transportation and storage of liquid hypochlorite by upgrading to on-site chlorine generation. This station is essential for the local water supply system and operates continuously.
Following a successful pilot study conducted in 2020, the CQM WATER & Mekorot team commissioned the new system, which caters to specific technical requirements.
The CQM WATER System is capable of supplying up to 300g of pure hypochlorite 24/7, while the reactor consumes electricity just 40% of the time. This allows substantial reduction of electricity costs. At the same time, due to the fact that hypochlorite is required at all times, a 12-hour supply of fresh hypochlorite (0.3%) is generated and stored in a nearby 1000L container.
Budapest, Hungary
Field study employing CQM WATER on-site brine add hypochlorite generation system:
This study was conducted during 2016-18 between CQM, Budapest water works, and InnoWater. The purpose of the project was to explore the innovative potential for smart, on-line, on-demand disinfection utilizing an electro-chlorination system to optimize chlorine usage in the urban water network of Budapest.
An electro-chlorination device capable of producing up to 50g/hour was installed at an old pumping station adjacent to the banks of the Danube. Several experiments were conducted for optimizing the anode type and brine conductivity.
Following the successful outcome of the project, one of CQM WATER’s electro-chlorination devices will be installed at one of Budapest’s network pumping stations.
CQM WATER’s on-site electro-chlorination devices will upgrade liquid chlorine facilities situated in densely-populated zones of the city, thus substantially reducing safety and health hazards.
Japan
Successful completion of lab-scale study resulted in purchase of CQM WATER portable electro-chlorinator
Metawater Japan is a global engineering company specializing in the design and construction of equipment for water treatment plants, sewage treatment plants, and waste treatment facilities; design, manufacture, and sale of various devices; implementation of repair work; and provision of services including operation management.
Water supply in Japan relies on surface water sources (~90%). Due to the presence of organic materials, disinfection of surface water generates some taste and odor issues, as well as substantial levels of DBPs.
A recent lab study that was conducted with the Metawater R&D team demonstrated the efficacy of CQM WATER’s electro-chlorinator in generating stable levels of hypochlorite from surface water samples, with & without added brine.
Following the successful completion of the study, CQM WATER supplied Metawater a portable electro-chlorinator which can be easily transferred to different locations upon demand. The portable device is capable of generating up to 100g/hour of 100% hypochlorite and will be utilized for various applications, such as in small wastewater facilities, as well as for disinfecting source water supply during emergency situations.
Malta
WSC Ta’ Kandja Pumping Station supplies approx. 300 cubic meters/hour of ground water. Following a successful pilot study conducted jointly with Mekorot in 2016, WSC upgraded its gas chlorine facility to CQM WATER’s on-site sodium hypochlorite generation equipment.
The slightly high level of chlorides enables the use of our system for producing hypochlorite directly from the source water, eliminating the labor and costs involved when using standard commercial products. The system produces 150g of pure hypochlorite on average while consuming 1.8 KWH.
By shifting to CQM WATER on-site hypochlorite generation technology, WSC benefits from several advantages, including:
Complete elimination of the risks associated with transporting & storing gaseous chlorine
Elimination of chemicals from the process (salt, soft water & cleaning acids)
Reduction of operational costs
Reduction of DBPs
Improved taste & odor of drinking water
It is estimated that the cost of upgrading the entire ~60 gas hypochlorite facilities to CQM WATER technology will result in a rapid ROI while resolving safety/health issues.
+972-3-973-2080
HAZORFIM 12 LOD